CTi Extension, AMRC
Extension of the existing Castings Technology International factory workshop and office areas based in the Advanced Manufacturing Research Centre, for the University of Sheffield.
![](/data/Case_Images/CTiartistsimpression02web.jpg)
![](/data/Case_Images/CTilogo01web.jpg)
![](/data/Case_Images/CTiGeneric02web.jpg)
The scheme was split into two projects. The main works consisted of the workshop extension and the secondary project included the office area extension.
A key element of both projects was to ensure minimal disruption of the ongoing processes being undertaken by CTi, who are the tenants in the University Building. The office works required a temporary decant of some staff members to other areas within the building while the works were completed.
Services:
-
- Project Management
- Principal Designer
Value: £4m
Construction Period:
-
- Office extension 6 months
- Workshop extension 12 months